PMP-Style Question 20 – Agile change management, backlog ownership

PMP Referenced Question 20: Resolving Sprint Failures Caused by Scope Volatility

This PMP-style scenario focuses on the project manager’s role in facilitating Agile collaboration and backlog management when the product owner introduces frequent new mandatory features during iterations.

📘 Scenario

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

❓ Question

What should the project manager do next?

  • A. Request the scrum team to prioritize the product backlog
  • B. Ask the product owner to prioritize the backlog with the project team
  • C. Call for an internal meeting to discuss the changes and their value
  • D. Incorporate the changes in the last sprint before the first release
⚠️ Disclaimer: This PMP-style question is presented for educational and commentary purposes only. It is not sourced from any official PMI exam and is not intended to violate any copyright. This content reflects interpretations based on the PMI mindset and principles, and is designed to help learners prepare for the PMP exam. If this question resembles real PMP exam content, it is coincidental and used solely under the doctrine of fair use for academic discussion. No claim of affiliation with or endorsement by PMI is made.

✅ Correct Answer: B. Ask the product owner to prioritize the backlog with the project team

✅ Why B is the Best Answer

In Agile (Scrum), the Product Owner owns the product backlog and is responsible for prioritizing features based on business value.

However, changes should:

  • Be discussed collaboratively with the team
  • Occur during backlog refinement or sprint planning
  • Respect the team’s capacity and velocity

By having the product owner prioritize with the team, the project manager:

  • Ensures the team’s input is respected
  • Encourages collaboration and transparency
  • Prevents mid-sprint disruptions, which violate Scrum principles

This action reinforces agile values like collaboration, respect, and sustainable pace.

❌ Why Other Options Are Less Effective

  • A. Request the scrum team to prioritize the product backlog
    🔻 Incorrect. The product owner owns backlog prioritization, not the Scrum team. The team can give input, but cannot take ownership of priority decisions.
  • C. Call for an internal meeting to discuss the changes and their value
    🔻 Incomplete. While a meeting can help surface concerns, it doesn’t resolve the structural issue of backlog management and repeated mid-sprint changes. Direct collaboration with the product owner is needed.
  • D. Incorporate the changes in the last sprint before the first release
    🔻 Risky. Accepting new features without reprioritizing can again jeopardize the sprint goal. This is reactive, not collaborative or strategic.

📌 Key Takeaways

  • Backlog prioritization is owned by the Product Owner
  • Sprint commitments must be respected — changes should go through backlog grooming, not injected mid-sprint
  • Team collaboration and transparency are core to Agile values

PMP candidates must understand Agile collaboration principles. Project managers must ensure that product owners and teams engage in prioritization to avoid sprint failures and protect delivery integrity.