PMP Referenced Question 15: Managing Risks During System Integration Projects
This PMP-style scenario tests how a project manager should respond to known production issues during a system integration effort. The correct response focuses on proactive risk management and impediment removal.
📘 Scenario
A company is working on a project to develop an integration of their existing systems. There are known issues in production.
❓ Question
What should the project manager do?
A. Identify and remove impediments and mitigate the risks
B. Ensure the product owner reviews requirements with the team
C. Include acceptance criteria in the definition of done (DoD)
D. Review the quality control processes and procedures
⚠️ Disclaimer: This PMP-style question is presented for educational and commentary purposes only. It is not sourced from any official PMI exam and is not intended to violate any copyright. This content reflects interpretations based on the PMI mindset and principles, and is designed to help learners prepare for the PMP exam. If this question resembles real PMP exam content, it is coincidental and used solely under the doctrine of fair use for academic discussion. No claim of affiliation with or endorsement by PMI is made.
✅ Correct Answer: A. Identify and remove impediments and mitigate the risks
🚧 Integration projects often **inherit risks** from existing production systems.
🛠 PMI encourages the project manager to **proactively identify, escalate, or remove impediments**.
📉 Known issues = known risks. They must be tracked and mitigated to protect the project scope and timeline.
✔ Why Option A is Correct
Proactively identifying and removing impediments aligns with PMI’s emphasis on risk management and adaptive leadership. The project manager must ensure these issues don’t block integration or introduce instability.
✖ Why Other Options Are Incorrect
B. Reviewing requirements is part of backlog grooming — but does not address live production issues.
C. Updating the DoD helps future deliverables but does **not mitigate current system issues**.
D. Quality control review is reactive. What’s needed now is **active risk and impediment resolution**.
📌 Key Takeaway
When production issues exist, project managers must act as **risk owners**. Removing impediments and mitigating risks is the fastest path to protecting integration progress and project delivery.
PMP candidates must know that early identification and resolution of risks and impediments are core duties of a proactive project manager. This ensures smoother delivery in integration-heavy environments.
PMP Referenced Question 22: Validating Budget Inputs for Analogous Estimation This PMP-style scenario focuses on avoiding estimation errors when using historical projects as a baseline. PMI...
PMP Referenced Question 21: Rebaselining a Delayed Project Through Change Control This PMP-style scenario focuses on how a project manager should respond when a project is...
PMP Referenced Question 20: Resolving Sprint Failures Caused by Scope Volatility This PMP-style scenario focuses on the project manager’s role in facilitating Agile collaboration and backlog...
PMP Referenced Question 19: Supporting Team Members Through Knowledge Gaps This PMP-style scenario tests how a project manager should respond to a team member’s performance issue...
PMP Referenced Question 18: Empowering Contractors Under Tight Project Deadlines This PMP-style scenario highlights best practices in empowering contracted teams during urgent rollouts. PMI encourages clear...