PMP Referenced Question 21: Rebaselining a Delayed Project Through Change Control
This PMP-style scenario focuses on how a project manager should respond when a project is significantly behind schedule. PMI emphasizes that formal change requests and governance through the Change Control Board (CCB) are required when baseline adjustments are needed.
π Scenario
A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule.
β Question
What should the new project manager do to address this situation?
A. Negotiate with the project sponsor immediately and establish a new project charter.
B. Modify the project management plan and get approval from relevant stakeholders.
C. Issue a change order to the change control board (CCB) and rebaseline the schedule.
D. Add more resources to recover the schedule without making changes to the baseline.
β οΈ Disclaimer: This PMP-style question is presented for educational and commentary purposes only. It is not sourced from any official PMI exam and is not intended to violate any copyright. This content reflects interpretations based on the PMI mindset and principles, and is designed to help learners prepare for the PMP exam. If this question resembles real PMP exam content, it is coincidental and used solely under the doctrine of fair use for academic discussion. No claim of affiliation with or endorsement by PMI is made.
β Correct Answer: C. Issue a change order to the change control board (CCB) and rebaseline the schedule
β Why C is the Best Answer
If the project is behind schedule and cannot meet the current baseline, PMI requires the project manager to:
Submit a change request to the Change Control Board (CCB)
Justify the impact on scope, time, and/or cost
Upon approval, rebaseline the schedule
This approach maintains transparency, stakeholder alignment, and process compliance.
β Why Other Options Are Less Effective
A. Negotiate with the sponsor and establish a new project charter
π» Not appropriate. The project charter is created once during initiation. It should not be revised to handle execution-level changes.
B. Modify the plan and get approval from stakeholders
π» Incomplete. All baseline changes must go through formal change control, not informal stakeholder updates.
D. Add more resources without changing the baseline
π» Risky. Adding resources may increase cost and doesn’t formally reflect the revised delivery strategy. Changes must be documented and approved.
π Key Takeaways
Baselines cannot be changed without formal change control
The CCB reviews and approves changes to the schedule baseline
Project charters are not revised to handle execution deviations
PMP candidates must understand that changes to the project baseline require formal approval through the integrated change control process. Rebaselining is not a casual decision and must be managed according to PMI standards.
PMP Referenced Question 22: Validating Budget Inputs for Analogous Estimation This PMP-style scenario focuses on avoiding estimation errors when using historical projects as a baseline. PMI...
PMP Referenced Question 20: Resolving Sprint Failures Caused by Scope Volatility This PMP-style scenario focuses on the project managerβs role in facilitating Agile collaboration and backlog...
PMP Referenced Question 19: Supporting Team Members Through Knowledge Gaps This PMP-style scenario tests how a project manager should respond to a team memberβs performance issue...
PMP Referenced Question 18: Empowering Contractors Under Tight Project Deadlines This PMP-style scenario highlights best practices in empowering contracted teams during urgent rollouts. PMI encourages clear...
PMP Referenced Question 17: Ensuring Accurate and Accessible Project Documentation This PMP-style scenario challenges the project manager's responsibility in maintaining accurate, up-to-date, and accessible documentation, especially...